|
Press releases
Austral Pacific Operations Update
Wellington, New Zealand - November 2, 2007 - Austral Pacific Energy
Ltd. (TSX-V: APX; NZSX: APX; AMEX: AEN)
Austral Pacific Energy Ltd., as operator of the Cheal oil field announced
today that the Cheal-A3X production well located at the main Cheal “A”
site has been temporarily shut-in due to mechanical problems. Preliminary
investigation work has indicated that pressure and fluid loss was caused
by a leak in the production casing.
The company has immediately instigated a review of remedial options for
the well, and at this stage it is planned that a temporary solution will
be in place by the second week of November, with the well brought back
into production at a reduced flow rate at that time.
A plan for a permanent solution has been put in place and the Company is
moving to secure the appropriate workover rig and personnel to implement
this plan. It is expected to take approximately four weeks to assemble the
equipment and complete the repair work. The Company expects to have final
repairs completed and the well returned to full production by mid to late
December, 2007.
Commenting on the shut-in, Mr. Thompson Jewell, President and CEO said,
“Everyone understands that mechanical problems of the sort we are
experiencing are part of the business. However, I am very confident that
our technical team will have the A3X well back in production with a
minimum of downtime and lost production.”
The Company also wishes to announce that the planned tie in of the B1, B2
and B3 wells into the Cheal Production Station is progressing according to
schedule. The wells, which are located at the satellite “B” site, were
shut-in as part of the planned, phased installation of the permanent
connections to the production facility. Despite extremely poor weather
conditions, testing of critical equipment such as switchboards and control
systems commenced ahead of plan and as a result the B wells are on
schedule to be returned to full production via the Production Station by
December 15, 2007.
Mr. Jewell said: “I am very happy with the progress of the tie-ins at
the “B” site. With these wells tied in we will be moving closer to
getting the field up to our planned long-term production rates. The
project is a relatively complex operation, and has drawn upon our team’s
skills in project planning, project management and project delivery, and I
am pleased to say that we are on schedule.”
Austral Pacific is a listed independent oil and gas exploration and
production company registered in Canada with corporate headquarters in
Wellington, New Zealand. The Company has an interest in thirteen
exploration and production permits totaling over 2.6 million acres in
onshore New Zealand and Papua New Guinea. The Company’s primary assets
are the Cheal Field, Kahili Field and Cardiff Field located onshore in the
highly prolific Taranaki Basin on the North Island of New Zealand. In
Papua New Guinea, the Company has an interest in four onshore blocks.
CONTACT: Investor Relations: Brad Holmes: +1 (713) 304 6062
Web site: http://www.austral-pacific.com
Email: ir@austral-pacific.com
|
|
Chairman's
report
| Company |
Code |
Released |
Type |
Headline |
| Austral Pacific Energy Ltd |
APX |
9 Aug, 2007, 15:48 |
HALFYR |
Management Discussion of the results released on 08/08/07 |
| Full Text of Announcement |
AUSTRAL PACIFIC ENERGY LTD.
BC FORM 51-102F1
(Expressed in United States Dollars)
(Unaudited - Prepared by Management)
For the Period Ended June 30, 2007
Overview
The Company is engaged in oil and gas exploration and production
in New Zealand and Papua New Guinea. This activity comprises:
- geological and geophysical studies to define targets for
drilling
- drilling and evaluation of exploration wells
- development and production of commercially viable discoveries
- use of infrastructure for own and third parties transport and
storage of hydrocarbons.
It is in the normal nature of the business that a portfolio of
projects is pursued at any time, and that individual projects
may never justify drilling. It is also the nature of the
business that a proportion of exploration wells that are drilled
will be unsuccessful. The Company typically acts as a member of
a joint venture group working through a phased work program
agreement, entered into with the appropriate regulatory body. In
each of New Zealand and Papua New Guinea, the regulatory body is
a state agency charged with administering the exploration for
hydrocarbons within its jurisdiction on behalf of the state. The
phased work program consists of a series of work steps,
typically on an annual interval, in which the subsequent step is
often contingent on the outcomes of the previous step. For
example, the commitment to drill a well in the up-coming permit
year may be contingent on the success in defining a drilling
target by seismic exploration in the previous year. The permit
holders will generally have the right at the end of a permit
year to commit to the next year's work program or relinquish
their permit rights.
Currency
Unless otherwise noted, dollar amounts refer to US dollars
throughout this filing
BOE Cautionary Statement
BOEs may be misleading, particularly if used in isolation. A BOE
conversion ratio of 6 Mcf: 1bbl is based on an energy
equivalency conversion method primarily applicable at the burner
tip and does not represent a value equivalency at the wellhead.
Date
The date of this filing is August 3, 2007, for the period ended
June 30, 2007.
Please refer to the Company's annual Management Discussion &
Analysis, filed on March 30, 2007, for further information,
which is updated below.
Overall Performance
The Company had a loss for the three months ended June 30, 2007
of $3.2 million.
The Company held cash and short-term deposits amounting to $3.9
million (this balance includes $3 million of cash that is held
in a restricted account required under the loan facility) as at
June 30, 2007. Cash held by the Company decreased in the quarter
by $2.2 million. This was a consequence of meeting operational
and overhead commitments.
Cheal Field
Petroleum Mining Permit (PMP) 38156 covering the Cheal Oil Field
was granted on July 26, 2006 for an initial term of 10 years.
There is a right to extend the term of the mining permit
following delineation of further reserves.
Extended production testing of the Cheal wells using temporary
test production facilities re-commenced on July 25, 2006. From
July 25, 2006 to June 30, 2007 a total of 80,390 barrels of oil
(100%) was produced. The oil was transported to the Waihapa
Production Station where it was sold to Swift Energy. Gas
produced in association with crude oil production was used to
generate electricity for on-site use and a small quantity was
sold into the local grid.
Construction of the Cheal oil field production facilities at the
Cheal A site commenced in Q3 2006. The facilities are expected
to be commissioned in August 2007.
Production will be from up to eight wells located at both the
Cheal A site and from a second site, Cheal B, located a
kilometre to the north. Engineering optimisation and design of
the facilities allow capacity to be significantly increased in
the future should this be required.
Development of the northern portion of the field from the Cheal
B site commenced in Q3 2006. Four wells have now been drilled
from the B site, three of which were completed as producers in
Q1 2007. The fourth well, Cheal B4, was an exploration well
which targeted Moki, Mt Messenger and Urenui sandstones to the
north west of the field's bounding fault. While the results at
the Moki level were disappointing, the well did confirm the
presence of hydrocarbon charge outside the currently recognised
limits of the field. A drilling program scheduled for 2008
targeting prospects north of the bounding fault has the
potential to add new reserves to the Cheal project.
The commercial arrangements for the storage and sale of the
crude oil have been completed.
Production in excess of 1,000 barrels per day (100%) is expected
to be achieved during Q4 2007. The drilling of A5, A6 and B4
sidetrack is expected to increase production in Q1 2008.
The Company is the operator of the Cheal project on behalf of
the joint venture, and owns a 69.5% beneficial interest in the
Cheal Field. An independent report by Sproule International Ltd
dated December 31, 2006, estimates 100% of 2P (proved and
probable) Reserves in Cheal to be 2.9 million BOE's and 3P
(proved, probable and possible) to be 4.1 million BOE's.
Cardiff Project
A series of flow and pressure build-up tests on the McKee
sandstone formation in the Cardiff 2A well conducted in 2006
resulted in flow rates which at times exceeded three million
cubic feet per day of gas and 100 barrels per day of light oil
and condensate.
On the basis that commerciality had been demonstrated from the
test of the McKee zone, the grant of PMP 38156 also included the
Cardiff Field.
The next step is to secure a flow test of the deeper K3E
reservoir interval. In preparation for this, the joint venture
acquired specialist fracture technology advice which, combined
with the results of the in-house reservoir simulation studies,
was used to design the testing programme for the K3E interval.
AUSTRAL PACIFIC ENERGY LTD.
A work over of the Cardiff-2A well and flow test of the K3E
interval began in late July 2007. Test results are expected by
early September 2007.
No reserves have yet been assigned to this property.
The Company is the operator of, and holds a 25.1% interest in,
the Cardiff Field.
Kahili
Production from the Kahili Field (PMP 38153) has been suspended
since November 2004. A re-interpretation of the seismic shows
the crest of the structure to be some 100 metres higher to the
north-east of the existing Kahili 1A/B well (Tariki sandstones).
It is intended to drill this up-dip potential in Q4 2007. As
production facilities have already been established in the
field, production will be able to be achieved with minimal
delay.
No reserves have yet been assigned to this property since being
written off in 2004.
The Company is the operator of, and holds an 85% beneficial
interest in the Kahili Field
Exploration and Appraisal Projects
The Company continues to evaluate its exploration portfolio to
high grade prospects and pursue the drilling of those that are
likely to have the most impact on the Company's growth.
New Zealand
PEP 38524 was granted on 8 March 2007 over an area of 2,187
square kilometers (offshore south Taranaki). In June 2007 a
total of 418 kilometers of aero - magnetic data was acquired. In
addition, reprocessing of existing seismic data and acquisition
of additional high quality seismic, in the first half of 2008,
is expected to identify drillable prospects in the permit.
The Ratanui-1 exploration well in PEP 38741 (onshore Taranaki)
was drilled in Q1 2007 to a depth of 2,120 meters. The target Mt
Messenger and Upper Moki Formation sands were intersected as
planned, however wireline log interpretation did not indicate
economic hydrocarbons. Ratanui-1 was plugged and abandoned.
Papua New Guinea
In Q3 2006 a total of 54 kilometres of 2D seismic was acquired
in PPL 235. This data has been used to better define the Douglas
structure and to confirm suitable appraisal well locations. The
data is also being used to delineate the nearby Puk Puk prospect
and other prospects in preparation for future exploration
drilling within the licence.
In Q1 2007 the PPL 235 Joint Venture signed a non-binding
memorandum of understanding with Alcan South Pacific to
investigate the supply of 40 billion cubic feet of gas per annum
over 20 years to the Gove Refinery in the Northern Territory of
Australia. The company holds a 35% interest in PPL 235.
A new licence, PPL 261, adjacent to PPL 235, was granted on 24
November 2006. The Company holds a 50% interest in PPL 261.
In June 2007 the Company received an offer from the Acting
Minister of Petroleum and Energy to extend the term of PRL 4
which the Company and the joint venture participants have
accepted. The joint venture is currently completing the
regulatory requirements for the award of the extension. The
Company holds a 28.9% interest in PRL 4.
Funding and risks
The Company considers it can meet all obligatory work
requirements out of existing funds, future production revenue
and by raising additional capital. As part of its ongoing
exploration portfolio management, the Company continually
assesses its equity holding in permits and may elect to farm-out
portions of certain commitments.
Following quarter end, and as referred to under the section
"Liquidity and Capital Resources", the Company raised
$10 million by way of privately placed preferred shares.
The Company is currently earning revenue from the sale of Cheal
oil from temporary production facilities. The Company expects
production of the Cheal field to be from permanent facilities
following commissioning in Q3 2007.
The Company faces a variety of business risks. The principal
ones relate to exploration failure, oil price, exchange rates
and the cost and availability of services and materials. If
current high oil prices continue, the Company will benefit
following Cheal permanent production. The Company's exploration
costs are made in both NZ dollars and US dollars. The Company
derives revenues denominated in US dollars providing a partial
hedge to the exchange rate fluctuations. Exchange rate movements
cannot be predicted. The Company maintains the bulk of its cash
reserves in US dollars.
Due to the recent high level of worldwide oil exploration
activity, exploration services and related materials are in high
demand and as a consequence have increased significantly in
cost, also due to the stronger NZ$ against the US$.
Results of Operations
Quarter Ended June 30, 2007
The Company's share of test production from Cheal has generated
revenue of $1,920,039 for the quarter ended June 30, 2007. The
other significant revenue was joint venture recoveries and
interest which totaled $462,714 for the quarter.
For the quarter ended June 30, 2007, the Company incurred a net
loss of $3,243,512 compared to a net loss of $1,949,505 for the
quarter ended June 30, 2006. The increased loss for the quarter
of $1,294,007 was primarily attributable to:
- in December 2006 the Company entered into a number of put
options and forward sales contracts for the future sale of crude
oil from the Cheal field. The fair value of the derivatives had
decreased for the period ended June 30 2007 resulting in a net
loss of $864,548;
- increase in depletion expense of $858,127 due to production of
oil from the Cheal field. There was no production during the
quarter ended June 30, 2006.
- increase in general and administrative expenses of $417,103.
This was primarily related to increased salaries and insurance.
The Company has increased the number of staff within the last 12
months to enable it to dedicate sufficient resources to
operational and administrative activities in order to implement
the Company strategy;
- Increase in interest expense of $353,566 and debt financing
expense of $480,791. This is the result of the Company drawing
down a debt facility from Investec Bank (Australia) Ltd in
December 2006. The Company did not have any borrowings for the
period ended June 30 2006.
- exchange loss of $60,034 relative to the June 2006 exchange
gain of $690,055.
offset by;
- net production (sales less royalties and production costs)
increased by $1,017,513;
- decrease in oil and gas exploration expenditure of $1,387,871
is primarily the result of the Company focusing on the capital
development of the Cheal oil field in the quarter ended June 30
2007. |
|
|